The section of Littlemoor Road between Chalbury Roundabout and the new road alignment is being resurfaced.
From Monday 18 July to Thursday 28 July, stop/go boards will be used between 9am and 4pm while the eastern end of Littlemoor Road and the Chalbury Roundabout area is resurfaced.
Tags: Littlemoor, press release
July 14, 2011 at 12:35 pm |
How do I find out whether vehicular access to and from Chalbury Close will be available during this activity?
I am disabled and need to be able to get onto Littlemoor Road.
I have been unable to get any response by phoning the Scheme Project Manager who is ‘out of office’ and no-one at his extension appears to know anything about this scheme which I find hard to believe.
July 14, 2011 at 2:27 pm |
Hi Terry,
Access to properties and onto Littlemoor Road will be available at all times.
It is likely that there will be only one day, during the second week of work, when the surfacing crew is directly outside Chalbury Close.