Night works ending

by

Manor railway bridge parapets (large version)

Night works at Manor railway bridge finish on Friday. The last few pre-cast parapet units will be lifted into place tonight and tomorrow night.

Over the next few months, the approach wing walls and parapets will be finished, the abutments will be backfilled and the deck of the bridge will be waterproofed.

The main structure of the bridge will be finished by March, with road surfacing and kerbs scheduled for the end of the summer.

Advertisements

Tags: , ,

2 Responses to “Night works ending”

  1. Mark Says:

    Does that mean the traffic nightmare at the Morrisons roundabout will continue until “the end of the summer”?

    As it was only planned for 4 months (i.e. end of Feb). When will things get back to normal there?

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: