September focus

by

This month the focus in the south of the scheme is to complete chalk stabilisation (which forms the base of the road) and start surfacing.

Work will also continue on drainage for the links between the relief road, Manor Roundabout and Mercery Road. 

On Lodmoor, the drainage basin and most of the final top-soiling will be finished and the foundation layers of the new park and ride will continue to be laid. 

In the north section tarmac has now been placed from the Ridgeway to Icen Lane, and work is continuning to complete all the kerbs and road drainage. 

Surfacing of footpaths and bridleways in this area will be almost complete by the end of the month. 

For Littlemoor Road and the area by the Littlemoor roundabouts work will be focussed on completing the drainage.

Advertisements

Tags: , , , ,

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: